When handover documents are requested in the last month of a job, the subcontractors who hold them have often moved to other sites. This guide sets out how to build a handover register at subcontract award, which certificates can hold up occupation, how to check documents as they arrive, and where software can help.

Quick answer

Start collecting handover documents when each subcontract is let. List every required O&M manual, warranty, certificate, test report and as-built drawing by trade, link each to the clause that requires it, and track receipt in a register. Building surveyors and certifiers may ask for certificates from practitioners before issuing an occupancy permit or occupation certificate, so missing documents can delay occupation.

Project coordinator sorting binders of operation and maintenance manuals on a table in a finished commercial lobby

What goes into a construction handover pack?

Oracle's Aconex documentation describes O&M manuals as usually including drawings, manuals, specifications, reports and warranties, across disciplines such as architectural, electrical, fire, hydraulic and mechanical. A full handover pack for a commercial building usually adds the items the client and the building surveyor or certifier need to operate and occupy it. Your specification and head contract set the actual list, so start there. Add anything the client's facilities manager has asked for, such as a particular asset register format, at the same time.

  • Operation and maintenance manuals for installed plant and systems.
  • Product and installation warranties, with start dates.
  • As-built drawings reflecting the final revisions.
  • Test, commissioning and inspection reports.
  • Certificates and statements from practitioners and installers.
  • Asset lists and maintenance schedules where the client requires them.

Why do handover documents run late?

Several causes are predictable. Documents are requested at the end, after the trade has demobilised and the person who knows the installation has moved to another site. Warranties need details such as serial numbers and installation dates that nobody recorded at the time. Manuals arrive as generic product brochures rather than documents for the installed equipment. Formats vary from scanned paper to links that expire. Each problem is cheaper to solve while the trade is still on site, which is the case for collecting progressively.

Track progress as the share of register lines received and checked, by trade, each month. A trade that is behind while still on site can be chased at the next coordination meeting; one that has already left needs phone calls, emails and sometimes a site visit to recover the same information.

How do you build a handover register at award?

Aconex's guidance notes that in most cases handover documents will have been specified in the original supplier contracts, and that collection can start at any point during the project. Use that. When each subcontract is let, read the specification and subcontract for handover requirements and create a register line for every document: trade, document type, the clause that requires it, the format required, the due date and the person responsible on the subcontractor's side. Set due dates ahead of practical completion, staged by trade, so the final weeks are left for checking.

Which certificates can hold up occupation?

In Victoria, the Building and Plumbing Commission says the building permit states whether an occupancy permit or a certificate of final inspection is needed on completion, that occupying a building before a required occupancy permit is issued is an offence under the Building Act 1993, and that the building surveyor may request certificates or statements from practitioners before issuing it. In NSW, Service NSW says you need an occupation certificate to occupy or use a new building, issued by the council or a private certifier. Ask your building surveyor or certifier early for the list of certificates they will want, and add each to the register.

How do you check documents as they arrive?

Check each document against the register line and the approved submittal before marking it received. A wrong or generic document accepted in month ten becomes a gap discovered at handover, when the supplier may no longer respond. Return anything that fails with a short note of what is missing and a new due date, keep the rejected version so the history is clear, and record who did the check and on what date.

  • It is for this project and this building, not a template from another job.
  • Product, model and serial numbers match the approved submittal and what was installed.
  • Warranty start dates, terms and the warrantor's details are complete.
  • Certificates are signed by the right practitioner and reference the correct work.
  • The file is legible, searchable and in the format the client specified.

Where can software help with handover documents?

Software can read the specification and subcontracts to draft the register, classify incoming documents by trade and type, compare warranty details against approved submittals, flag generic or mismatched documents, chase overdue items and build an index of the final pack by trade and location. It cannot certify that work complies, accept a document on the client's behalf or decide whether a substitute product is acceptable. Those decisions stay with the project team, the consultants and the building surveyor or certifier.

Handover documents by type

DocumentUsually fromCheck on arrivalWhen to request
O&M manualsTrade subcontractors and suppliersMatches installed equipment, not a generic brochureAt award, due before commissioning
WarrantiesSuppliers, manufacturers and installersProduct, location, installer and start dateAt installation
As-built drawingsDesign and construct trades, consultantsLatest revision, reflects site changesAs each area is completed
Test and commissioning reportsServices trades and commissioning agentsSigned, dated, all systems coveredAt commissioning
Practitioner certificatesInstallers and practitionersCorrect practitioner, correct scopeFrom the surveyor's or certifier's list, early
Asset and maintenance listsServices tradesComplete against the equipment scheduleBefore practical completion

Practical checklist

  • The handover register is built from the specification and subcontracts at award.
  • Each trade has a due date for its documents ahead of practical completion.
  • The building surveyor's or certifier's certificate list is obtained early and in the register.
  • Every warranty records product, location, installer and start date.
  • Documents are checked against approved submittals before being marked received.
  • The final pack is indexed by trade and location and tested by someone outside the project team.

Common questions

When should we start collecting O&M manuals?

At subcontract award, by putting the requirement in the register with a due date. Aconex's own guidance says collection can start at any point during the project. Collecting as each trade completes its work means the people who installed the equipment are still available to answer questions.

Can we hold retention until documents arrive?

That depends on your subcontract wording and on security of payment law in your state, which in some states restricts how payment can be made conditional. Get legal advice before using payment to enforce document delivery, and make the document obligations clear in the subcontract from the start.

What format should the handover pack be in?

Whatever the client specifies, usually digital and searchable, indexed by trade and location. Platforms such as Aconex have dedicated handover tools. Agree the format and structure with the client early so documents can be filed into it as they arrive.

Who checks that warranties are valid?

The project team checks that each warranty is complete and matches what was installed. Whether a warranty meets the contract requirements, or what it covers if something fails, is a question for the contract administrator and, where needed, a lawyer. Record the check in the register.

What should happen to handover documents after practical completion?

Give the client the indexed pack in the agreed format and keep your own copy with the project records. Warranties and as-builts are often needed during the defects liability period, when a returning item has to be traced to its installer and product. Keep the register as well, because it shows what was received, when, and who checked it.