Missing a payment schedule deadline can leave a head contractor liable for the full amount a subcontractor claimed. The risk is largely administrative: a claim can arrive attached to an email sent to someone on leave, or by post to a site office. This guide sets out an intake process and the response windows in four states, as general administrative information rather than legal advice.

Quick answer

Register every incoming payment claim on the day it is received: who served it, how, when, the amount and the subcontract, then assign a named person to decide between paying in full and serving a payment schedule. A payment schedule is due within 10 business days in NSW and Victoria and 15 in Queensland and WA, or sooner if the contract says so. This is general information, not legal advice; confirm your position with a construction lawyer.

Contract administrator date-stamping a printed subcontractor payment claim beside an open diary in a Brisbane site office

Why does the date a claim arrives matter so much?

Under each state's security of payment Act, the response window runs from when the claim is served or received, not from when someone opens it. NSW Government guidance says that if you do not provide a payment schedule in time you are liable for the full amount claimed, and that in adjudication you cannot raise reasons that were not in your schedule. Victoria's Building and Plumbing Commission says the same about liability for the full amount, and adds that the claimant may suspend work. In Queensland, the QBCC says failing to pay by the due date without a payment schedule is an offence carrying a penalty of up to 100 penalty units.

What counts as a payment claim?

The definition differs by state, which is why screening should not be left to whoever opens the email. In Western Australia, the Small Business Development Corporation says a payment claim must be in writing, state the amount, describe the work and state that it is made under the 2021 Act. The QBCC's guidance refers to a "payment claim or invoice", so in Queensland an ordinary invoice from a subcontractor should not be assumed to fall outside the regime. A safe administrative rule is that every request for payment for construction work or related goods and services goes to the claims register first, and the claims owner decides how to treat it.

What should the claims register record?

The register should let anyone see, at a glance, which claims are open and when each response is due. Record the facts of service separately from the date someone noticed the claim, because they can differ by days. Keep the original email or envelope with the claim. Hold the register in one place for the whole company rather than per project, so a claims owner covering leave can see every open item, and close an entry only when the outcome and proof of service are filed.

  • Date, time and method of receipt: email, post, platform, hand delivery or site office.
  • Claimant, subcontract reference and the period or reference date claimed.
  • Amount claimed and whether the claim says it is made under the Act.
  • Response deadline, with the rule used and who set it.
  • Claims owner and backup, and the outcome: paid in full, schedule served, or referred to a lawyer.

How do you work out the response deadline?

Start with the Act for the state where the work is done, then read the contract, because a shorter contractual period applies where the Act allows it. Count business days, not calendar days. Victoria's regulator says a business day there excludes weekends, Victorian public holidays and the period from 22 December to 10 January. Service rules matter too: the BPC says a payment schedule sent by post is served 7 business days after posting unless it is delivered earlier, so a schedule posted late in the window can miss the deadline. Have a second person check every deadline the claims owner sets.

What must a payment schedule contain?

The regulators in NSW, Victoria and Queensland describe the same core contents: identify the payment claim, state the amount you propose to pay (which can be nil) and give all your reasons for paying less. NSW guidance says reasons not included in the schedule cannot be raised later in adjudication, and the QBCC stresses listing every reason. The administrative work is gathering the evidence quickly enough for the contract administrator to write those reasons: site diary entries, the variation register, defect records, back charges and the subcontract terms. A register that links each claim to that evidence shortens the time to a decision.

Where can AI help, and where must it stop?

Software can watch every inbox and the platform for documents that look like payment claims, extract the claimant, amount and date received, open the register entry and alert the claims owner and backup on the same day. It can assemble the evidence pack and draft a schedule for review. It must not set the final deadline, decide the scheduled amount or serve the schedule. Those steps belong to the claims owner, with legal advice where the claim is disputed. The value is that no claim sits unread while the response window runs.

This guide covers four states only. For work in South Australia, Tasmania, the ACT or the Northern Territory, check that jurisdiction's legislation and regulator before relying on any timeframe here.

Payment schedule windows in four states

StateActPayment schedule dueIf no schedule is given in time
New South WalesBuilding and Construction Industry Security of Payment Act 199910 business days after the claim is received, or earlier under the contractLiable for the full amount claimed; contract-based defences cannot be raised
VictoriaBuilding and Construction Industry Security of Payment Act 2002 (amended from 15 April 2026)10 business days after service, or sooner under the contractLiable for the full amount; claimant may seek adjudication, go to court or suspend work
QueenslandBuilding Industry Fairness (Security of Payment) Act 201715 business days after being given the claim, or earlier under the contractFull amount payable; failing to pay by the due date is an offence
Western AustraliaBuilding and Construction Industry (Security of Payment) Act 202115 business days after receiving the claim, or a shorter contract periodClaimant may apply for adjudication

Practical checklist

  • Every project has a named claims owner and a named backup.
  • Claims sent to personal inboxes, site offices or the platform reach the register the same day.
  • The register records how and when each claim was served, not only when it was opened.
  • Deadlines are set by the claims owner using the state Act and the contract, and checked by a second person.
  • Nothing produced by software is served on a claimant without the claims owner's sign-off.
  • A construction lawyer has reviewed the process for each state you build in.

Common questions

Does a subcontractor's invoice count as a payment claim?

It can, depending on the state and what the document says. The QBCC refers to a "payment claim or invoice", while in WA a claim must state that it is made under the Act. Route every request for payment through the claims register and let the claims owner, with legal advice where needed, decide how to treat it.

What if the claim was emailed to someone on leave?

The response window does not pause because the recipient is away. Set up forwarding from project mailboxes and personal inboxes to the claims register, and consider naming a claims address in your subcontracts. Victoria's regulator lists the contract's method of service and any method the claimant has accepted among the valid ways to serve a schedule, so check your contract terms with your lawyer.

Can we add reasons for withholding payment later?

Plan as if you cannot. NSW guidance says you cannot raise reasons in adjudication that were not included in the payment schedule, and the QBCC tells respondents to list all reasons. That is why the evidence pack needs to be assembled early in the window, not on the last day.

Does a pay-when-paid clause give us more time?

In Victoria, the Building and Plumbing Commission says a pay-when-paid provision has no effect, and the 2026 amendments restrict such provisions further. You cannot delay paying a claim because you are waiting on your own client. Ask a lawyer how this applies in other states and to your contract.

Can software calculate the deadline for us?

It can suggest a date from the received date, the state and the contract period, and show its working. A person should confirm it, because public holidays, holiday shutdown periods, service by post and contract terms all affect the answer. Treat the software's date as a draft that the claims owner signs off.

Sources and further reading